南通永芳仓储厂精炼油技改项目桩基工程施工组织设计南通房屋建设工程有限公司2008 年 1 月 1 日目 录1、编制说明···················31.1 编制依据···················31.2 编制原则···················32、工程概况···················32.1 工程地质情况·················32.2 工程概况···················43、施工总体部署·················53.1 施工总平面布置················53.2 项目管理部··················53.3 施工队伍安排·················74、施工资源配备·················74.1 施工机械配备·················74.2 劳动力使用计划················75、施工总进度计划················86、主要施工方法·················86.1 施工准备···················86.2 打桩施工工艺流程···············96.3 打桩施工顺序················106.4 打桩作业··················106.5 施工要领及施工注意事项···········116.6 桩基部分检验项目方法和质量标准·······127、工程质量管理体系及保证措施·········127.1 质量目标和质量方针·············127.2 质量标准··················137.3 质量保证体系················137.4 质量保证措施················148、施工安全保证措施··············158.1 工程安全管理目标··············158.2 安全技术规程、规范和规定··········158.3 安全措施··················169、文明施工及环境保护·············169.1 文明施工措施················169.2 环保措施··················171.编制说明1.1 编制依据1.1.1 南通永芳仓储厂精炼油技改项桩基工程招标文件;1.1.2 现行国家有关施工技术规范及质量检验评定标准,江苏省有关标准、本公司施工的同类、相关工程项目施工经验和成果。本施工组织设计所涉及的技术...