Day/Date天/日期Test试验PurposeofTest试验目的Testactivities试验活动Remarks备注Day1第1天11/08/2006Rotorrun-in:转子试转:Cranktest摇转试验1.Listenforrubsorunusualnoises听是否有摩擦和异常噪音2.Functionaltestofemergencytrip-button紧急跳闸按钮的功能试验3.Purgespeedcrankingforrotorvi-brationcheck以吹扫速度摇转,检查转子振动情况4.MonitorLCIstartingtempera-turesandoperation监视器LCI起动温度和运行5.Airblowingth-epurgepipingofD5andPM4gasfuelduringcrank摇转期间给D5和PM4吹扫管鼓风6.Checkoperationofliftoilandturn-inggear检查顶轴油和盘车的运行1.Rollupto50rpmtripbyDCSemergencypushbut-to-nand200rpmandtripbyGTMK6controlemergencystop通过DCS紧急按钮逐渐增加到50rpm,通过GTMK6控制紧急停机跳闸2.Re-start,acceleratetogotoPurgespeedfor5minandselectnormalstop重起,加速到吹扫速度5分钟,选择正常停止3.Re-start,holdatpurgespeedandairblowingth-epipingofD5andPM4,tripbyDCScustomertrip(L4CT)after30Mincranktest重起,保持在吹扫速度,给D5和PM4管道鼓风,在30分钟摇转试验后通过DCS客户跳闸(L4CT)跳闸4.Verifycoastdowntoturninggear核实惰行至盘车5.Monitorvibrationlevelsthrough-outthetestperiod监视整个试验期间的振动级?Useautostart-upsequencestopreparetheunitfora“Ready-to-Start”采用自动走动顺序将机组准备好“准备起动”?Rubchecksareperformed检查摩擦?ADREvibrationmonitortobeconnected连接ADRE振动监视器AfterShut-down停机后?Reinstatethepipingspool-ofD5andPM4pipeworkaftershutdown停机后重新恢复D5和PM5管子的导管Day1第1天11/08/2006Rotorrun-in:转子试转:Falsefir-ing,actualfirst-firingandFSNL假点火,实际第一次点火和FSNL1.Falsefire假点火2.ActualFirstFiretoFSNL实际第一次点火至FSNL1.Selectfireforfalsefireandcheckunitfor-gasleaks,andP2pr.Check选择假点火的火,检查机组是否漏气,和P2。检查2.Verifyunittripandcoastdowntoturn-inggear核实机组跳闸,惰行至盘车3.Actualfirstfiringandcheckfor-gasleaksatfiringspeed实际第一次点火,检查点火速度时是否漏气4.AccelerationunituptoFSNLandstabi-lizedmin4hoursthermalsoak5.Startupheatercommissioning将机组加速到FSNL,至少稳定4小时热浸泡6.Normaldownunitandkeepturn-inggearonfornaturalcooldown.机组正常停机,保持盘车,自然冷却7.Monitorvibrationlevelsthrough-outthetestperiod监视整个试验期间的振动级AfterShut-down停机后1.Installbalanceshotsifrequired如果需要,安装平衡粒2.Repairanyleaks/defectsidentified修复发现的泄漏/缺陷3.ReplaceorcleanthestrainersofLPHoodspray,CEP,BFPanddrainssprayandperformanyothermainte-nanceitemsasrequired更换或清洁低压罩喷嘴、EDP、BFP和疏水喷嘴的滤网,根据需要执行其它维护项4.Inspectandcleanstartuptemporarygasstrainersandsealing/coolingairifrequiredtoclean检查和清洁起动临时气体滤网和密封/冷却空气(如果需要清洁的话)Day/Date天/日期Test试验PurposeofTest试验目的Unitactivities机组活动Remarks备注Day/Date天/日期Test试验PurposeofTest试验目的Testactivities试验活动Remarks备注Day2第2天11/09/2006Rotorrun-in:转子试转;StartupandFSNL起动和FSNL1.FSNLandheatsoakfor4hoursFSNL和热浸泡4小时1.Startnormal-ly,gotoFSNLandstaythereifvibrationlevelsacceptable正常起动,至FSNL,如果振动级可以接受,保持2.Electricaltest电气试验1)Shaftvoltagetest轴电压试验2)ACimpedancetest交流阻抗试验3)MaintransformerShortcircuittestwiththeconnectionofGeneratorbyEX2100power通过EX2100电力连接发电机做主变压器短路试验4)OpencircuittestbyEX2100,Thetestvoltagewillbevariable-from0Vto20.52KV(1.08PUof19KV)通过EX2100做开路试验,试验电压从0V至20.52KV(19KV的1.08PU/)5)Meggercheckforsealcasingandbearing(T8)atcollectorendside用迈格表检查收集器端侧...