南京南站综合枢纽快速环线龙西互通二期工程防撞护栏施工方案编制:审核:审批:中铁十五局集团有限公司南京南站综合枢纽快速环线龙西互通二期工程NZ-LX-B1标二〇一六年十二月目录一、工程概况.......................................................................1二、编制说明.......................................................................22.1编制依据...................................................................22.2编制原则...................................................................3三、施工组织.......................................................................43.1施工组织安排...............................................................53.2施工进度计划...............................................................8四、施工技术方案...................................................................84.1施工准备...................................................................84.2施工工艺流程图.............................................................94.3钢筋制作与安装.............................................................94.4模板施工..................................................................114.5防撞护栏混凝土施工........................................................144.6防撞护栏模板拆除及养护....................................................15五、质量保证措施..................................................................165.1组织机构..................................................................165.2质量保证措施..............................................................16六、安全保证措施..................................................................176.1安全管理目标..............................................................176.2安全保证体系..............................................................186.3安全生产组织和管理保证措施................................................196.4施工现场安全技术措施......................................................216.5保证人身安全措施..........................................................226.6保证施工安全措施..........................................................246.7施工现场安全用电措施......................................................256.8施工机械安全措施..........................................................266.9施工现场治安消防、防火安全保证措施........................................276.10混凝土防冻措施...........................................................286.11防滑措施.................................................................296.12安全应急救援预案.........................................................29七、文明施工措施及环境保护措施....................................................327.1文明施工管理措施..........................................................327.2文明施工技术措施..........................................................347.3环境保护措施..............................................................357.4文明施工规划..............................................................35第0页共47页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第0页共47页防撞护栏施工方案一、工程概况龙西立交位于南京南站西南角,是机场高速与宏运大道相交的节点。现状宏运大道地面主干路下穿机场高速和集散车道,龙西立交一期EN和SE两条右转匝道已实施完成,已沟通宏运大道地面主干路和机场高速东侧集散车道。二期实施NE、ES两条左转匝道和WS右转匝道联系宏运大道地面主干...