济宁北湖省级旅游度假区安置社区东北片区1#楼附着升降脚手架工程施工方案编制:审核:批准:编制单位:济南四建(集团)有限责任公司脚手架公司编制日期:年月日目录一、编制依据····················································3二、工程位置及概况··············································3三、泰山牌JT02-1导轨式液压升降脚手架的概况及技术参数··········3四、济宁北湖省级旅游度假区安置社区东北片区4#地块1#楼施工方案··························································5(一)架体结构计算··········································5(二)机位布置··············································8(三)施工组织安排··········································9(四)施工工艺流程··········································9(五)施工方法及技术要求····································91、架体安装············································102、附着升降脚手架升、降··································153、附着升降脚手架的使用·································174、脚手架拆除··········································195、附着升降脚手架安装质量要求···························19五、安全措施····················································201、安全技术要求·········································202、安全组织保障·········································213、安全技术有关规定·····································22六、施工计划····················································231、进度计划··············································232、材料与设备计划········································233、劳动力计划············································24七、施工配合····················································24八、设备使用中常遇到的故障及处理方法····························24九、附着升降脚手架检查评分表···································25十、拆除方案···················································27十一、应急预案·················································34附图:1、机位布置平面图2、竖向留孔位置图3、附墙支座与建筑物固定详图4、脚手架立面图5、临时找平架施工图6、临时支撑固定导轨主框架详图7、断开处架体搭设详图济宁北湖省级旅游度假区安置社区东北片区4#地块1#楼附着升降脚手架工程施工方案一、编制依据:1、工程设计施工图纸及总平面图2、《建筑施工附着升降脚手架管理暂行条例》建设部建字[2000]230号文3、...