一重石化筒节车间淬火水槽基础建设施工组织设计编制单位:大连宏蔚建设有限公司二零一七年一月二十二日目录一、编制依据........................................................1二、工程概况.........................................................12.1工程主要情况.................................................12.2建筑概况.....................................................22.3结构概况.....................................................2三、工程特点与难点及解决措施:.......................................33.1工程特点与难点...............................................33.2解决措施.....................................................3四、施工部署.........................................................44.1项目施工目标.................................................44.2、进度安排及施工顺序..........................................44.3管理组织结构设置图集主要岗位工作职责.........................44.4新技术的运用.................................................9五、施工进度计划.....................................................95.1施工部署原则.................................................95.2施工段划分及施工程序.........................................95.3施工进度安排................................................10六、施工准备与资源配置计划..........................................126.1施工准备....................................................126.2资源配置计划................................................126.2.1劳动力投入计划.........................................126.2.2主要材料、设备供应投入计划.............................14七、主要施工方案....................................................167.1基础工程....................................................167.2主体工程....................................................187.2.1模板工程................................................187.2.2钢筋工程................................................377.2.3大体积混凝土工程........................................42八、施工平面布置....................................................59施工现场布置总体思路......................................59主体结构施工场地要求......................................60施工平面布置图............................................61施工临时用水、用电计算....................................62九、保证措施........................................................669.1工期保证措施................................................669.2保证工程质量的技术措施......................................699.3、安全生产保证措施...........................................789.4、文明施工保证措施...........................................829.5环境保护措施................................................86十、应急措施........................................................88一、编制依据1、业主提供的全套施工图纸。2、《建筑工程施工质量验收统一标准》(GB50300-2001)3、《混凝土结构工程施工质量验收规范》(GB50204-2002)4、《混凝土结构设计规范》(GB50010)5、《大体积砼施工规范》GB50496-20096、《块体基础大体积混凝土施工技术规范》(YBJ224-91)7、《泵送混凝土施工技术规程》(JGJ/T10-95)8、《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)9、《滑动模板工程技术规范》(GB50113-2005)10、《建筑施工手册》第四版11、《高层建筑施工》第三章,大体积砼施工12、《施工技术标准汇编》QB/JGSJ-01-2006(本公司企业标准)13、类似工程的经验。二、工程概况2.1工程主要情况工程名称:高能探伤室工...