中铁建设集团有限公司xx分公司ChinaRailwayConstructionGroup,ZhengzhouBranchXX人才产业区钢筋工程施工方案编制人:审核人:审批人:编制单位:中铁建设集团有限公司xx分公司第xx项目部编制日期:2016年06月01日目录一、编制依据.....................................................11.1、工程建设文件..............................................11.2、有关规范、规程、标准和图集................................1二、施工部位的工程概况............................................12.1、工程简介..................................................12.2、钢筋工程结构设计概况......................................22.3、钢筋砼保护层..............................................3三、施工准备......................................................43.1、施工特点分析..............................................43.2、项目部管理组织结构及项目部人员职责........................43.3、劳动力筹备................................................53.4、技术准备..................................................53.5、施工机械布置及需求........................................63.6、材料准备..................................................83.7、流水段划分示意图..........................................83.8、检验试验..................................................9四、工期保证措施.................................................114.1、总体施工管理安排.........................................114.2、工期保证措施.............................................12五、主要施工工艺流程及方法.......................................135.1、钢筋施工的工艺流程.......................................135.2、钢筋放样.................................................135.3、钢筋加工.................................................145.4、钢筋绑扎.................................................175.5、钢筋焊接连接.............................................215.6、具体部位钢筋绑扎.........................................215.6.1.马凳.................................................215.6.2.基础底板钢筋绑扎.....................................225.6.3.柱箍筋绑扎...........................................235.6.4.剪力墙钢筋绑扎.......................................245.6.5.框架梁钢筋绑扎.......................................275.6.6.顶板钢筋绑扎.........................................305.6.7.平屋面与车库框架梁钢筋绑扎...........................305.6.8.后浇带钢筋绑扎......................................315.6.9.钢筋堆放.............................................335.6.10.成品钢筋检验........................................33六、质量要求.....................................................336.1、质量验收.................................................336.2、试验取样.................................................346.3、质量主控项目.............................................356.4、质量一般项目.............................................356.5、质量允许偏差项目.........................................366.6、应注意的质量问题.........................................37七、成本控制措施.................................................37八、成品保护.....................................................38九、安全、环保措施及绿色施工技术应用.............................389.1、施工安全措施.............................................389.2、环境保护措施.............................................399.3、绿色施工技术应用.........................................3...