射洪县省级财政现代农业示范园奖补资金产业基地排灌渠系建设项目施工组织设计编制:审核:审批:目录第一章工程概况及编制依据···························································3第一节工程概况··············································································································3第二节编制依据··············································································································3第三节编制原则··············································································································3第二章确保工程质量的技术组织措施···················································4第一节质量规划··············································································································4第二节施工质量管理组织机构及其主要职责··········································································5第三节质量保证技术措施·································································································11第三章确保安全生产的技术组织措施···················································13第四章确保文明施工的技术组织措施及环境保护措施····································17第一节文明管理措施·······································································································17第二节环境保护措施·······································································································19第五章确保工期的技术组织措施························································22第六章施工方案和项目经理部组成人员·················································24第一节施工组织机构·······································································································24第二节施工顺序·············································································································24第三节施工测量·············································································...