用于明标正本大方古城斗姥阁、莲花塘恢复重建工程(项目名称)/标段施工招标投标文件投标文件内容:技术标投标人:(盖单位章)法定代表人或委托代理人:(签字或盖章)日期:2011年1月21日目录一、施工方案与技术措施········································································(1)二、质量保证措施和创优计划·································································(26)三、施工总进度计划及保证措施······························································(54)四、施工安全措施计划··········································································(59)五、文明施工措施················································································(67)六、施工场地治安保卫管理计划······························································(71)七、施工环保措施计划··········································································(72)八、冬季和雨季施工方案·······································································(74)九、施工现场总平面布置·······································································(81)十、现场组织管理机构··········································································(86)十一、与发包人、监理及设计单位、专业分包工程的配合·····························(96)一、施工方案与技术措施一、工程测量和施工放线认真学习和充分熟悉设计图纸和工程施工部署,并针对本工程的平面布置制定切实可行的测量放线方案和顺序,是确保工程质量,确保工程顺利进行的重要措施和关键工序。1、测量放线方案采用根据总平面图、规划红线以及定位依据,施测出的轴线控制桩制作控制点,以纵横轴线控制点为依据,钉龙门桩和龙门板,将轴线位置标注在龙门板上,作为工程施工的几何尺寸的基准线。2、测量放线1、设立工程测量专业小组,由项目副经理负责。测量小组要专人负责制,项目施工员负责计算、施测轴线和控制点,并配备2名专职放线人员。2、执行一切定位放线均须自检、互检后,由专职质检员验收和项目工程师复验,并经监理、建设单位工程师复核验收。3、放线、验线的依据要原始、正确、有效,做好完善的放线和验线记录。4、项目工程师验线时必须从基准点开始,认真复核检查,不得马虎从事,或以点代面,对轴线要进行闭合验收,减少差误。验线工作完成后,填写定位记录,交由项目经理审核签字,并须由建设单位和监理公司核签。5、复核、验收完毕的各轴线控制点,标高控制点和龙门桩、板要做好保护工作,防止碰撞变形。对基准轴线控制点和标高控制点要做半永久性保护,以便施工过程中的复核使用。3、仪器工具的使用和保管1、使用器具:DJ2-2型光学经纬仪一台和SZ型工程水准仪一台,标尺l50米钢卷尺2把,3米钢卷尺4把,5公斤线坠1只2公斤线坠2只和1公斤。2、线坠2只以及其它辅助工具。3、专人使用,专人保管,专人护理,使用中做到轻拿轻放,正确操作。4、经纬仪和水准仪平时注意使用,加强养护。正常情况下,工程开工前必须检验...