南通永芳仓储厂精炼油技改项目桩基工程施工组织设计南通房屋建设工程有限公司2008年1月1日目录1、编制说明···················31.1编制依据···················31.2编制原则···················32、工程概况···················32.1工程地质情况·················32.2工程概况···················43、施工总体部署·················53.1施工总平面布置················53.2项目管理部··················53.3施工队伍安排·················74、施工资源配备·················74.1施工机械配备·················74.2劳动力使用计划················75、施工总进度计划················86、主要施工方法·················86.1施工准备···················86.2打桩施工工艺流程···············96.3打桩施工顺序················106.4打桩作业··················106.5施工要领及施工注意事项···········116.6桩基部分检验项目方法和质量标准·······127、工程质量管理体系及保证措施·········127.1质量目标和质量方针·············127.2质量标准··················137.3质量保证体系················137.4质量保证措施················148、施工安全保证措施··············158.1工程安全管理目标··············158.2安全技术规程、规范和规定··········158.3安全措施··················169、文明施工及环境保护·············169.1文明施工措施················169.2环保措施··················171.编制说明1.1编制依据1.1.1南通永芳仓储厂精炼油技改项桩基工程招标文件;1.1.2现行国家有关施工技术规范及质量检验评定标准,江苏省有关标准、本公司施工的同类、相关工程项目施工经验和成果。本施工组织设计所涉及的技术参数若与正式工程有差异,将根据正式施工图纸、资料在施工方案中进行修订和补充。1.2编制原则1.2.1在投标、施工、竣工和服务的全过程中执行我公司建立并已通过认证的GB/T19002-ISO9002质量体系,并始终如一地将工程施工的质量目标定为优良。1.2.2加强科学管理,充分做好施工准备,合理组织施工,在最短的时间内实现工程的竣工。1.2.3狠抓工程质量、安全、环境,确保施工顺利进行。1.2.4坚持工期、质量和经济效益并重,优化编制施工方案,在保证工期、质量的前提下降低业主建设投资。2.工程概况2.1工程地质情况详见岩土勘查报告2.2工程概况南通永芳仓储厂精炼油技改项桩基工程位于南通开发区。本桩基工程桩型为静压管桩桩,工程量为89根。3.施工总体部署3.1施工总平面布置3.1.1临时设施:施工现场不设大临设施,办公用房采用集装箱式工具房,生活用房就近租用民房。3.1.2施工用水根据招标文件中所述,由业主提供的施工用水接点接入,桩基施工用水量不大,仅需生活用水。3.1.3施工用电由甲方提供的施工用电线路接出,在打桩区域设置一个动力配电箱。施工用电用95mm2电缆从配电箱接出。3.1.4施工场地打桩场整由业主负责,先清除地面杂物及表层耕植土,打桩场地内应有良好的排水系统,打桩过程中保证场地干燥无积水。3.1.5桩材供应现场桩材的存量应不少于三天的打桩量。3.2项目管理部3.2.1项目组织机构框图3.2.2项目部职责1)全权代表公司履行与甲方商签的施工合同,并对施工合同的履行负全面责任。2)负责编制工程项目施工计划。3)负责编制施工组织设计(或施工方案),经公司总工程师审批后实施;组织施工方案、施工技术措施、设计交底(图纸会审)的编制、审批工作。4)设专职质量检查员,代表公司行使“...