外墙及窗边渗漏维修方案目录一、总体目标......................................................................................................................................1二、管理人员职责..............................................................................................................................1三、整改实施方案..............................................................................................................................13.1渗漏维修流程........................................................................................................................13.1.1整体工作流程..............................................................................................................13.1.2维修工程流程.......................................................23.2试水及渗漏排查要求.............................................................................................................23.3渗漏原因分析.........................................................................................................................23.3.1外墙渗漏原因分析......................................................................................................23.3.2窗边渗漏原因分析......................................................................................................23.4渗漏维修.................................................................................................................................23.4.1外墙渗漏......................................................................................................................23.4.2窗边渗漏.....................................................................................................................33.5主要防水堵漏工具.................................................................................................................3四、资源计划表..................................................................................................................................3五、验收流程......................................................................................................................................4六、保障措施......................................................................................................................................4七、质量保证及安全文明施工..........................................................................................................47.1质量保障措施........................................................................................................................47.2成品保护措施..........................................................................................................................57.3安全文明施工........................................................................................................................57.3.1安全施工........................................................................................................................57.3.2文明施工........................................................................................................................6一、总体目标1、2017年11月29号完成外墙渗水大面修补;2、2017年11月30号前完成窗边渗水大面处理。二、管理人员职责1、现场总负责人工作职责1)负责与业主及政府相关部门沟通交流,统领整个项目的整改事宜;2)熟悉整改技术方案,并对分栋整改负责人进...