目录1.编制依据······························32.工程概况······························32.1 基础工程概况·····························32.2、工程难点·······························53、施工准备·····························53.1、技术准备·······························53.2、机具准备·······························63.3、材料准备·······························83.4、现场布置······························113.5、施工前准备·····························123.6、环境影响准备····························134、施工安排·····························134.1、工期安排······························134.2、大体积混凝土浇筑管理人员组织及其职责················144.3、劳务以及负责人···························164.4、现场劳动力安排···························165、主要施工方法···························175.1、施工段的划分····························175.2、测量放线······························185.3、前序施工······························195.4、钢筋工程······························195.5、模板工程······························225.6、混凝土工程·····························235.7、后浇带施工·····························335.8、预埋件处理·····························356、底板混凝土浇筑的应急措施····················356.1、成立应急指挥小组······················...