漳州台商投资区奥特莱斯大道工程后张法 13m 空心板梁预应力张拉方案及计算书中铁二局奥特莱斯大道项目部2014-6-18目 录一、张拉条件................................................................1二、张拉方法................................................................1三、张拉程序................................................................1四、锚具、钢绞线............................................................1五、钢绞线的穿束............................................................1六、千斤顶、油表............................................................1七、张拉操作................................................................1八、实际伸长量的计算和测量..................................................2九、伸长率的计算............................................................2十、预应力钢束的封头........................................................2十一、施加预应力的注意事项..................................................2十二、根据标定报告计算出压力表读数和张拉力对比表............................2十三、钢绞线伸长量计算......................................................4十四、孔道压浆..............................................................6十五、安全措施..............................................................6十六、预应力施工人员和机具统计表............................................7后张法 16m 空心板梁预应力张拉方案及计算书一、张拉条件砼强度达到设计强度 100%以上,并且混凝土龄期不小于 14d,方可张拉。二、张拉方法所有钢绞线均采纳两端对称张拉,张拉采纳以张拉力控制为主,以伸长量做校验,实际伸长量与理论伸长量的误差控制在 6%以内。如发现伸长量异常应停止张拉,查明原因。三、张拉程序0→初应力(10%)→25%应力→50%应力→75%应力→1.0 应力(持荷 2min)后锚固,张拉顺序为:13.0m(h=0.7m)简支梁张拉顺序为:左 N1→右 N2→右 N1→左 N2, 钢束应对称交错逐步加载张拉;四、锚具、钢绞线本工程采纳 YM15 系列锚具。钢绞线采纳 15.2mm 钢绞线。锚具和钢绞线均由厂家出具产品检验书,并送有关检测单位进行效验。五、钢绞线的穿束钢绞线采纳人工编束后...